(this means we can build!)
Needs list
o Cow poop and food waste!
o Fencing
o Financially: Need to submit a purchase request to AS unless it’s under $25 and one for BP must be under $50.
· Need to decide what materials we still need
· Price out materials and write a proposal?
· Need drill and band saw (have them on campus).
· Need a test schedule for once it has been started.
o Someone will need to check on it and test it everyday but don’t need to check pH everyday.
· Need to figure out to make temperature about 85F.
o Could build a little greenhouse (or but it in outback’s?) but plan for now is to wrap it with insulation and black tarp to keep heat in.
o Most efficient would be something in the bin.
o Use thermo coupler (DMM) to check temperature in the waste, possibly in multiple locations.
Can start building this week with materials that we have.
· Health and safety approved hole depth as well.
· Tori will go to a meeting later this week, possibly this Wednesday, to discuss where we can build and hopefully designate the space we need.
o If no meeting she will talk to Steve Shaw or Melanie to talk about site.
· Could build at the Outback on the site.
Decide to start building this Wednesday 8-10
· Store materials in the plastics lab.
· Dig hole on a Saturday so professional members can come (outback has tools).
Plan of action
· Forrest will talk to Chris Kenny about how to get food waste.
o Need to decide how to chop food, distinguish big chunks of food from smaller pieces (filter through a screen).
o Look for a machine to process waste to make it smaller.
· Figure out how to make thermo couplers (talk to Nikki).
· Need to buy supplies (especially for more buckets) as well as submit a request to AS for the money.
o Cinderblocks or wood and fencing (snow fence), insulation, big black tarp.
o Hannah will find out about money and then we will go get all supplies.
· Make signs to warn people (possibly Kinko’s, copy or publishing center).
· Talk about Amy’s reimbursement.
Next meeting: Monday 3/3 (talk about money, acquiring waste, thermo coupler, talk about how construction went, update material list).
Try to get supplies in between
3/8 Saturday Dig hole and install digester if it’s ready.